TIME
FRAME
|
PAPERWORK
|
Preliminaries
|
Prepare
Declaration
of Default
|
Start
|
Prepare
Pre-Lien/Demand letter
|
30 days after Pre-Lien Letter
|
Prepare
and record Notice of Delinquent Assessment and Claim of Lien
(NODA)
|
|
30
days after recording the NODA
|
Prepare
and record Notice of Default and Election to Sell (NOD). Order
Trustee’s Sale Guarantee (TSG).
|
|
10
days after the recording of the NOD
|
10-Day
Mailings
|
|
30
days after the recording of the NOD
|
30-Day
Mailings
|
|
2
months after the
recording of the NOD
|
Authorization
to Publish Non-Military Affidavit
|
|
3
months after the
recording of the NOD
|
Prepare
Notice of Sale Order TSG Update
|
|
No
later than 20 days prior to sale
|
Publish,
Post and Mail Notice of Sale
Record
Notice of Sale
|
|
Sale
Date
|
Conduct
Sale
Prepare
and record Trustee’s Deed Upon Sale
|
|
90
Days from Trustee’s Sale
|
Right
of Redemption Period
90
days after the Trustee’s sale per Civil Code 1367
|